The Mumbai-Ahmedabad high-speed rail project crossed a visible threshold on Sunday: the country's largest rail tunnel boring machine, a 13.6-metre Mixshield, began excavation at Vikhroli for the 5.8-km drive to the underground Bandra Kurla Complex terminus. A formal flag-off by Railway Minister Ashwini Vaishnaw was called off amid heavy rain, but the ministry ordered work to start immediately rather than wait for a fresh date.
A second machine, under assembly at Sawli in Thane district, is expected to be ready within days. It will bore the 9.7-km stretch towards Vikhroli that includes the 7-km section under Thane Creek, which would be India's first undersea rail tunnel. Between them, the two machines account for most of the roughly 21-km underground approach between BKC and Shilphata; the balance is being mined conventionally.
For MMR property watchers the milestone matters on two counts. It hardens the case for BKC's next decade, since the terminus anchors a district that already commands some of India's priciest office stock, and it keeps attention on the Vikhroli-Kanjurmarg belt, where large private land holdings sit directly on the alignment.
Timelines still depend on how the machines cope with basalt and creek-bed geology. But after years in which the Maharashtra section trailed Gujarat's viaducts, tunnelling at Vikhroli is the clearest sign yet that the Mumbai end is catching up.
Sources
Business Today: Rail ministry postpones launch event, orders work to begin immediatelyFree Press Journal: India's largest rail TBM begins tunnellingChannel I AM: Bullet train tunnel boring launchFinclara Dispatch briefings summarise publicly reported developments for context. Registry figures shown are a growing sample from Finclara's ledger, not the whole market. Informational only — not investment advice.
← More from the Dispatch